General info only. Check with a licensed pro and your local building department.

The time limits in the statute itself (C.R.S. 38-22). Miss one and the lien can be lost.

Quick dates: lien deadline dates tool.

What the sources say

TopicWhat the source saysSource
Notice of intentAt least 10 days before filing the lien statement, serve the owner and the prime contractor by personal service or registered/certified mail (return receipt), and record an affidavit of service with the statement.Source page
checked 2026-11-02
What the statement saysOwner name, claimant, who furnished the work, contractor (if you are a sub), property description and amount due; signed and sworn.Source page
checked 2026-11-02
File within 4 monthsMost claimants: before 4 months after your last labor or materials.Source page
checked 2026-11-02
Day/piece laborLabor by the day or piece, without furnishing labor or materials: within 2 months after completion.Source page
checked 2026-11-02
Sue within 6 monthsThe lien ends after 6 months from last work or completion unless you start a lawsuit and record a notice of it within that time.Source page
checked 2026-11-02

Not confirmed yet

  • Unknown Exceptions under 38-22-109(10)-(11) for your job — talk to an attorney.